By Todd C. Davis, Teri Rizvi
 Facts
Size: 50-acre urban brownfield
Land Cost: $25 million
Estimated Development Costs: Could exceed $200 million
Location: Intersection of Brown Street and Stewart Street, Dayton, Ohio
Current status: Phase I completed (i.e. all buildings have been demolished
and the part of property has been remediated). Phase II: Balance of property is
being remediated
Project Team: Hemisphere Advisors LLC—Brownfield Redevelopment Advisor; Hull
and Associates LLC—Environmental Consultant; Burt Hill—Land Planner
Case Study Overview On the
fringe of Dayton, Ohio, sits prime riverfront property. Although it´s been
called the most developable piece of property in the city, it´s largely vacant,
a ghost of its heyday as the bustling site where National Cash Register (NCR)
manufactured its cash registers.
...
You need to register to view the rest of the article. Click here to subscribe.
|
|
|
Renewal Magazine
|
|
With the Washington budget showing no signs of a quick-and-easy resolution, federal brownfields programs are unlikely to get much of …
|
Brownfields and crop development—for the express intent of producing foods—are concepts that have always been strange bedfellows. Mutually exclusive. An…
At this abandoned, blighted factory—consisting of 187,227 square feet in 21 different structures on 13.5 acres in the three…
PROJECT GOAL: To revitalize land that had been sitting idle for years by putting the property back into productive…
|
|
Industry Profiles
|
|
|
|
Vicky Keramida Indianapolis
president and CEO of KERAMIDA Environmental, Inc.
|
|
|
|
|
Brownfield Stateside Report
|
by Staff Report
In Michigan, some are predicting a better business climate for redevelopment and regulatory closure of contaminated properties thanks to a bill Michigan Governor Rick Snyder was scheduled to sign last week. The new regulations should have a positive impact on commercial real estate development and brownfields redevelopment resulting in the creation of jobs. |
|
by VeruTEK
A property located on a bank of the East River and in a densely developed residential and commercial area, had its work cut out for it from an environmental remediation standpoint. The mission was to clean up the land and ultimately make one puzzle piece to a larger urban revitalization project that would be redeveloped as a public library and park ranger station.
|
| view all |
|
|
Industry Events
|
|
Submit Event
|
|
Industry Experts
|
|
|
|
Susan Boyle
Mt. Laurel
Senior Environmental Practice Leader, GEI Consultants
|
|
|
|
|
|